Cranes & Lifting

Crane Lift Plan Checklist With an Owner for Every Item

Settle the load, radius, ground and crew before the crane is booked, confirm papers before it leaves the yard, and give every item a named owner.

Key takeaways

  • A lift plan is written down, not agreed by phone. It grows more detailed as the lift gets more complex or risky.
  • Ask in writing who writes and who approves the plan. It differs by project, supplier and client.
  • Weigh the load and measure the radius at pick and set before you choose a crane.
  • Ground, underground services, overhead lines and weather limits are checked before the crane arrives, not when it is on site.
  • Ask for the inspection certificate, its expiry date and the operator and rigger papers before the crane leaves the yard.

This crane lift plan checklist is for a site manager or engineer who has a crane booked, or is about to book one. A lift is often delayed or stopped because one item was left to "someone else": the ground, the papers, the signaller. Work through the three stages below and write a name next to every line.

What is a lift plan and who writes it?

A lift plan is a written plan for one lift or one series of similar lifts. It sets out:

  • the load;
  • the crane and its configuration;
  • the rigging;
  • the lift area;
  • who does what;
  • what happens if something goes wrong.

The more complex or risky the lift, the more detail the plan needs. A light, simple lift may need a short plan. A heavy lift near people, buildings or live services needs a full one, prepared by someone competent. Never skip the plan, even a short one.

Who writes and approves the plan differs by project, supplier and client. Sometimes the crane supplier prepares it. Sometimes the contractor does, and the client or site owner approves it. Ask who is responsible, in writing, before you book.

Before you book: load, radius, height and site facts

The lift decides the crane. Collect these facts first and give them to the supplier.

  1. Load weight. Use a weighed or documented figure, not a guess. Add the weight of the rigging and any spreader beam or lifting frame hanging with the load. The chart notes say whether the hook block and ropes are already deducted, so the supplier confirms it.
  2. Centre of gravity, where known. An uneven load changes how it must be rigged.
  3. Radius at the pick and at the set. Radius is the horizontal distance from the crane's centre of rotation to the load. Check each lift at its own radius and weight: the worst case decides the crane. Measure carefully, because the boom bends under load and the real radius can be a little larger than a drawing shows.
  4. Hook height needed to clear the structure at the set point.
  5. Boom length and the chart configuration the supplier plans to use.
  6. Site facts: access route, working space, nearby structures and the lift duration.

Capacity falls as radius grows, so a crane that looks big enough on paper may not lift your load at your radius. See how to read a crane load chart, and how to choose crane capacity for measuring each figure.

Tip. Send the supplier the weight, the pick radius and the set radius as three separate numbers. "A 20-tonne crane" is not a lift requirement.

The crane and the crew: who and what the supplier brings

Before the crane leaves its yard, ask the supplier for these items.

  • the crane's current inspection certificate and its expiry date;
  • the operator's competence documents;
  • the rigger's competence documents, if the supplier provides the rigging crew;
  • the chart configuration for your radius;
  • confirmation of who writes the lift plan.

Check that the certificate has not expired and covers the crane that will arrive. See what to check on lifting equipment inspection certificates and how to check an operator's competence.

Common mistake: collecting papers only when the crane reaches the gate. If something is missing, the crane waits and the lift may be refused. Ask a few days earlier.

Ground, access and the lift area

Ground is the part of a lift most often assumed. Settle it before positioning:

  • Ground strength. Assess the ground under the crane and its outriggers for the crane's weight plus the load. The supplier can give the outrigger load, and the ground must carry it without settling. Fresh fill, loose sand, excavation edges and soft areas need particular care. Ground that looks firm is not proof.
  • Mats or spreader pads. If the ground needs help, agree who supplies them and what size.
  • Underground services. Check for pipes, cables, drains and basements under the crane position and its route in.
  • Access. Confirm the crane can reach the position: gate width, turning space and overhead clearance.
  • Overhead obstructions and power lines. Treat every line as live. The safe distance is set by the utility and the site rules. Ask for it. Do not estimate it.

Mark an exclusion zone with barriers or tape so that nobody walks under or near the load path. See banksmen and exclusion zones.

Rigging, communication and weather limits

Rigging. It must suit the load's weight, shape and lift points, and no accessory is loaded past its marked limit. See rigging basics: slings, shackles and working load limits.

Communication. Agree one signaller and one set of signals or one radio channel. The operator should take instructions from that person only. The one exception is a stop signal: anyone may give it, and the operator obeys at once.

Weather. Agree stop conditions before the day. Wind limits come from the manufacturer's data for that crane, and a load with a large surface area may need a lower limit. Ask the supplier for the figure and how wind will be measured. In Saudi Arabia heat and dust may also affect people and equipment, so agree breaks, water and what happens if visibility drops. Requirements differ by project, site owner and insurer: confirm them before mobilising.

On the day: the pre-lift briefing and stop conditions

Before the first lift, hold a short briefing with everyone involved. Cover:

  1. What is being lifted, its weight and where it goes.
  2. The route of the load and the exclusion zone.
  3. Who is the signaller and what the signals are.
  4. The wind and weather limits.
  5. Who has the authority to stop the lift.

Then confirm the setup matches the plan: crane position, outriggers extended and set on the mats as the chart requires, and the crane level.

Stop the lift if:

  • the ground moves or the crane settles;
  • the weather passes the agreed limit;
  • someone enters the exclusion zone;
  • the signaller or radio link is lost;
  • the crane's load moment indicator alarms or the operator asks to stop;
  • the load, rigging or setup differs from the plan.

If the plan no longer matches the site, stop, set any suspended load down if it is safe to do so, and update the plan. Never override a crane's safety alarms to finish a lift.

Checklist table: item, who owns it, done

Copy this table into your site documents. The owners shown are typical. Change them to match your contract, and never leave one blank.

StageItemTypical ownerDone
Before bookingWho writes and approves the lift plan is agreed in writing.Customer and supplier
Before bookingLoad weight and centre of gravity confirmed.Customer
Before bookingRadius at pick and at set, hook height.Customer
Before bookingCrane size, boom length and chart configuration.Supplier
Before lift dayInspection certificate and expiry date received.Supplier
Before lift dayOperator and rigger competence documents received.Supplier
Before lift dayGround assessed for crane plus load; mats agreed.Site
Before lift dayUnderground services checked.Site
Before lift dayOverhead lines and safe distance confirmed with the utility.Site
Before lift dayAccess route and crane position confirmed.Site and supplier
Before lift dayRigging suits the load; every accessory's marked limit checked.Supplier or rigging crew
Before lift dayWeather stop limits agreed.Customer and supplier
Before lift daySignaller and signals or radio channel named.Site
At the liftExclusion zone marked and kept clear.Site
At the liftPre-lift briefing held; stop authority named.Site
At the liftSetup matches the plan.Supplier and site
At the liftStop conditions understood by everyone.Site

How to do this on Maedah

When you post a crane request, enter the machine, the city and the site on the map, and the dates. Put the load weight, pick and set radius, and hook height in the request details. Add the requirements you need, such as a driver, insurance, TÜV inspection or Urgent.

Sealed quotes line up side by side. Compare what each includes, then ask each supplier in chat for the certificate, operator papers and who writes the plan. You can also browse cranes and boom trucks before you post.

Common questions

Who is responsible for the crane lift plan?

It differs by project, supplier and client. Sometimes the supplier writes it; sometimes the contractor does and the client approves it. Before you book, ask in writing who writes it, who approves it and who holds the final copy.

How detailed does a lift plan need to be?

Detail rises with how complex or risky the lift is. A simple, light lift in an open area needs a short plan. A heavy lift near people, buildings or live services needs a full one. If unsure, ask the supplier and the site owner, and write down what they say.

What should a crane lift plan checklist include?

It should cover load weight and centre of gravity, crane and chart configuration, radius at pick and set, boom length, ground, services and overhead lines, rigging, signaller, exclusion zone and weather limits. Each line needs a named owner and a done tick.

When should I ask the supplier for the crane's papers?

Before the crane leaves its yard, ideally a few days before lift day. Ask for the current inspection certificate with its expiry date, and the operator and rigger competence documents. Checking at the gate leaves no time to fix a gap.

Who decides the safe distance from power lines?

The utility and the site rules set it, not an estimate by you or the crane supplier. Treat every line as live. Ask the utility and the site owner for the figure in writing before the crane is positioned.

Find the equipment

Browse the machines this guide talks about.

These guides give general information to help you plan. They are not engineering, legal or insurance advice. Always follow the manufacturer's instructions, your site's safety rules, and the requirements of the authorities and your insurer.

Keep reading

Safety, Inspection & Maintenance

Banksman and Exclusion Zones on Site: Rules for Crews

Keep people out of the area a machine can reach or the operator cannot see, and give every blind manoeuvre one trained banksman. Mark the zones and brief the crew.

9 min read