Planning a Project

Construction Equipment Schedule by Phase: Matrix and Rules

List the project phases, give each phase its own machines and dates, and request specialist machines first. Hire each machine for the period it works, not for the whole project.

Key takeaways

  • Split the project into phases and give every phase its own machines, dates and request.
  • Do not start a machine until the task before it is finished and approved, so write that task next to the machine in the plan.
  • Size cranes and lifts per phase. The heaviest lift in one phase may not be the heaviest in another, so list the load, radius and height for each phase.
  • Plan site services (power, lighting, water, cabins, toilets) as a separate line that runs across all phases.
  • Request specialist machines, such as large cranes and piling rigs, before general machines like excavators.

This is for contractors, site managers and owner-builders who have a scope of work and a start date but no equipment plan. It turns the scope into a construction equipment schedule by phase. You will settle which machines each phase needs, what must be ready before each one starts, and how early to ask for it.

Why plan equipment by phase instead of hiring for the whole project?

Each phase needs a different mix of machines. Excavators are busy at the start and often idle later. Cranes and concrete pumps matter during the structure. Lifting platforms and tools matter during finishes.

Hire one fleet for the whole project and some machines wait. Hire with no plan and a machine arrives before the work is ready, or the reverse. A phase plan fixes both: each request has exact dates.

Which machines belong to each phase?

A building project usually moves through six phases: site preparation and earthworks, foundations, structure, envelope and finishes, services and external works, and handover. Your project may merge or skip some of them, and a multi-building site may have each building in a different phase at the same time. Write your own phase names, with start and finish dates, on one page.

Use the matrix below as a starting point. The last column matters most: a machine can start only when the task before it is ready.

PhaseTypical machine roleWhat must be ready first
Site preparation and earthworksExcavators and loaders to clear, cut and fill; trucks to move material; compaction equipmentBoundary and levels marked, access agreed, utilities located
FoundationsExcavation to the design depth; piling rig where the design needs piles; concrete delivery and a pump; a light crane for reinforcement cagesApproved excavation, reinforcement and formwork in place and approved to pour
StructureTower or mobile crane for steel, precast and formwork; concrete pump; telehandler or forklift for materialsPrepared crane stand, approved lift plan, concrete pour approved
Envelope and finishesLifting platforms, scissor lifts and boom lifts for facade and ceilings; hoists; a crane for facade panels or for heavy equipment such as air-conditioning units lifted to the roof; small toolsStructure complete in the area, safe access and firm, level ground or floor for the platform (check the floor's load limit)
Services and external worksExcavators for trenches; compaction; paving and road equipment for external areasService routes marked, existing buried services located, drawings approved
HandoverCleaning and defect-fixing access equipment (lifting platforms, ladders); removal of cabins and temporary worksInspections done, client agrees the sequence

Never skip a "ready first" item to save time. If the site is not ready, the machine may stand on site and you may still be charged for it.

Do not size the crane once for the whole project. Foundations may need only a light lift for reinforcement cages, the structure the heaviest lift at the widest radius, and finishes a different lift, such as facade panels or rooftop equipment. For each phase, list the heaviest lift, its radius and its height, then ask the supplier to confirm a machine for that phase.

Browse excavation equipment, lifting equipment and concrete equipment.

Which equipment runs across every phase?

Some items run from the first day to handover:

  • Site power and generators
  • Lighting for early starts and night work
  • Water supply and storage
  • Site cabins, offices and storage containers
  • Toilets and welfare facilities

Plan these as a separate line, not inside any phase. They often start before the first machine arrives and end after the last one leaves. Ask whether the supplier can relocate them as the work moves, and who pays.

How do you find overlaps, gaps and idle machines?

Draw one grid: phases across the top, machines down the side, a mark where a machine works. This example for a small building has no dates, and merges some columns:

MachineEarthworksFoundationsStructureFinishesExternal works
Excavatorworkworkwork
Concrete pumpworkwork
Cranework (light lift)work (heaviest lift)work (facade panels)
Lifting platformwork
Site generatorworkworkworkworkwork

Add start and finish dates to each mark, then check three things.

Overlaps. Two phases often run at the same time in different areas. Foundations may still be going on one side while the structure starts on the other. Count the machines for both phases at once.

Gaps. Look for a phase where the work stops because a machine is missing or late. For example, no excavator when the next area is ready.

Idle machines. Look for a machine booked across a wait. For example, a crane hired for the structure phase and left on site during a slow period. Either release it or agree in writing what is charged while it waits.

Whether an idle machine is charged depends on the agreed terms. Write the dates, the hours per day and what happens to delays into the request, then confirm them in the quote.

Tip. Compare the cost of keeping the machine on site with the cost of delivering it again, and with the risk that it is not available when you need it. Ask the supplier for both figures before you decide.

How early should you request each machine?

Use one rule: the fewer machines of that type, the earlier you ask.

  • Specialist machines. Large cranes and piling rigs are usually fewer than general machines, and availability varies by city and season, so request them earlier. Ask as soon as the phase date is firm.
  • General machines. Excavators, loaders, trucks and small tools are easier to find, so request them later.
  • Anything that needs a site-specific plan. A crane needs a lift plan (see the crane lift plan checklist) and a prepared stand. Piling needs the design and the access agreed. Allow time for that, and for any approvals the site owner or municipality requires, before the machine arrives.

To find the real lead time, ask each supplier how much notice they need for that machine and city. Then put the request date on your schedule that far before the phase start, with extra margin for specialist machines. Work back from the start date of the phase, not of the project.

In Saudi summer, site hours and concrete pours are often moved to cooler hours, so the dates for pump and crane requests may need to change. Strong wind, including during dust and sand storms, can also stop crane lifts, so keep a margin. Confirm working hours with the site owner before fixing dates, and see planning equipment around Ramadan and summer schedules.

Before you post each request, write down:

  • The phase start and finish dates
  • The task that must be ready first, and who confirms it
  • The hours per day the machine will work
  • Site access for delivery trucks and the machine itself
  • Who relocates site services when the work moves

What changes when the project is not a building?

The method stays the same: list the phases, attach machines, find the "ready first" item. Only the phase names and the machines change.

For a small residential build, start with equipment for building a villa.

Note. Sizing the number of machines per phase is a separate question. See how to estimate how many machines a project needs.

How to do this on Maedah

Post a request for each phase when the phases are far apart. A Maedah request carries the machines, quantities, city and site, dates and requirements such as a driver or insurance. When phases follow each other closely, one project request can hold several machines.

Compare the sealed quotes side by side, and agree price and payment with the supplier. For wording, see what to write in an equipment rental request.

Common questions

How do I make a construction equipment schedule by phase?

List your phases with start and finish dates. Under each, write the machines and the task that must be ready before each one starts. Add a separate line for site services that run across all phases. Then mark overlaps and gaps, and decide which machines to request first.

Should I hire all machines for the whole project?

Usually not. A fleet booked for the whole project includes machines that sit idle in phases that do not need them. Hire each machine for the period it works, and keep for the full project only what runs across all phases, such as site services.

Which machines should I request first?

Request the machines that are fewer and harder to find first. Large cranes and piling rigs go earlier than excavators, loaders or small tools. Ask as soon as the phase date is firm, and confirm the site and the lift or piling plan with the supplier.

Do I need a separate request for every phase?

Use a separate request when phases are far apart, so each one has exact dates and comparable quotes. When phases follow each other closely, one project request can hold the machines for both. If a phase slips and a booked machine would arrive early, tell the supplier as early as possible and ask what the booking terms allow.

Find the equipment

Browse the machines this guide talks about.

These guides give general information to help you plan. They are not engineering, legal or insurance advice. Always follow the manufacturer's instructions, your site's safety rules, and the requirements of the authorities and your insurer.

Keep reading

Planning a Project

Equipment Needed to Build a Villa on a Small Plot

On a small plot, the gate, the street and the overhead lines decide which machines can work. Hire the few you need, rent the rest only for the days they are used.

9 min read
Planning a Project

Plan Machines for Ramadan and Summer Work Schedules

When Ramadan or summer cuts your usable hours, you need more machine-days, more machines or a night shift. Set the hire terms and site support before the machines arrive.

8 min read